How long does it take to build a modular house? Week-by-week schedule

Detailed schedule of modular house construction: from contract to keys. See exactly what happens each week.

Kategoria

Guide

Czas czytania

8 min

Data publikacji

2026-04-04

How long does it take to build a modular house? Week-by-week schedule

8–16 weeks. That's the standard delivery time for a Treevia modular house from contract to move-in. But what exactly happens during this time?

Week-by-week schedule

Weeks 1–2: Design and administration

  • Final technical design or adaptation
  • Building notification or permit submission
  • Foundation type selection based on geotechnical survey

Weeks 2–4: Parallel work begins

  • On site: foundation construction
  • In the hall: CNC cutting, panel assembly, insulation, membranes

Weeks 4–8: Production and assembly

  • Finished panels transported to site
  • Assembly by crane – structure erected in 1–3 days
  • Roof, windows, external doors installed

Weeks 8–12: Interior finishing

  • Electrical and plumbing installations
  • Plastering, painting
  • Flooring, sanitary fittings

Weeks 12–16: Final touches (larger models)

  • Terrace, external cladding finishing
  • Utility connections
  • Final inspection and handover

Why so fast?

  • Parallel processes – foundation and production happen simultaneously
  • No weather delays – hall production regardless of season
  • No subcontractor coordination – one team, one schedule
  • Fixed price – set before start, no changes

Summary

Building a house in short time is not marketing – it's a real advantage of prefabrication technology. 8–16 weeks from contract to move-in, no winter breaks, no budget surprises.